11-23-20 The sprinkler room is taking shape. Carter Sprinkler is killin it…
Carter is doing a GREAT job and is on schedule !!!
11-21-20 Eversource shows up with new poles to get the power in for the new enclosed storage building
And they save the day getting us power.
11-10-20 Craig and the Nutter crew are getting 300+ feet of pipe in the ground/day !!!!
The race is on!!!! The race against time, before it snows…
11-04-20 Nutter is laying that 1 foot pipe in ASAP !!!!
Another couple days they’ll be down at the building. Exciting stuff !!!!
11-03-20 Two shiny new water Hyrdants- Soon to be installed on our sprinkler water line !!
Please keep the dogs away !!!!!
10-30-20 Nutter Excavating is digging and installing 1300 feet of 1 foot main water pipe for our sprinkler system in the new Premium Pontoon Storage building !!
NOTHING is too good for your nice Bennington, Crownline and Bayliner Boats. This is the newest, cleanest building, most secure building in the Northeast !!!!
10-19-20 And we have a nice flat laser guided concrete floor !! Good Job Cullen Concrete. Thanks Roland!!!!
They started at 7am Monday with the first of 50 concrete trucks. The polishing crew finished up at 4am Tuesday. That’s a long day !!!!
The laser guided mini-grader sets the final grade for Nutter Construction to compact the gravel well in anticipation of the floor being poured !!
Monday the 19th Cullen Concrete brings in 50 cement trucks to lay out a nice level floor. Bring it on !!!!
10-16-20 Thanks to Hutchin’s Electric- The new Premium Storage Building has LIGHTS !!!
Now Cullen Concrete can pour the floor next Monday !!! Thanks for all your help Jim !!!
10-07-20 Lots of new Bennington and Crownline Boats going into our nice clean Premium Boat Storage Facility !!!
Winnisquam Marine is taking care of all those nice new boats !!!!