08-07-17 A GREAT day to be pouring the footings for the boat rack piers !!

Cool and dry. It doesn’t get any better…
08-05-17 Anchor bolts set by Mas-Con. The center piers will be poured starting Monday. Construx to start erecting building #1 Monday!!

Actually mobilizing onto the site with their equipment and moving building #1 onto the site!
08-05-17 Most of the rear 220ft wall poured and the forms stripped.

Looking very good. Great progress.
08-01-17 8am Laying out the foundation for building #2. Mas-Con has 2 crews onsite and they are cranking out the concrete foundation.

Definitely cruising along now- these guys mean business !!!!
08-01-17 Back filling and compacting the foundation for building #1. Just waiting for Construx now !!!!

Bring it on…
07-30-17 Nutter construction has the rear wall excavation ready to pour. Looking very good, Nutter has moved on to building #2

The rear wall is 22o feet long. The building is 109 feet deep. Almost 45 feet tall. Should fit 250 boats in here, 4 levels tall…
07-28-17 The concrete is 100% ready for Building #1. 100% ready to go !!!! Bring it on !!!!

Ya, We’re ready !!!!
07-22-17 The first concrete pier has the form peeled off and now it’s curing awaiting Construx to start the building assembly !

So far – so good…
07-22-17 Mas-Con has poured all the footings and several of the piers for building #1. This building will hold 96 boats.

96 boats, 3 high in racks. Construx should be standing this building up sometime in the next 2 weeks !!!!
Nutter Construction is manufacturing structural fill for the new building platforms !!

They sort the fill, crush some rocks and pile the fill up ready for use.