08-25-17 Building #2 foundation is ready and waiting for building #2. The floor will be poured first 9/5+9/6.

Bring it on….
08-25-17 The 230v and the low voltage 3 inch conduits are in the trenches !!! All set for electrical power and our 32 camera 4K resolution security cameras…

Looking good for all the powered systems…
08-25-17 Roofed!! Building #1 is roofed by Construx. Can’t wait for the side walls !!!!

Make your winter storage reservation and tell us, “you want to be in building #1”.
08-21-17 Monday 8am. The Construx crew is still killing it….

More rake trim. More Purlins. Roofing soon…
08-17-17 5:43pm All this in one day !!! Construx is ALMOST as fast as Winnisquam Marine-

ALMOST, Not Quite!! Â The crew at Winnisquam Marine is the fastest and bestest there is. Period !!!!
08-17-17 Building #2 is buzzing along too !!!! Nutter and Mas-Con are killing it big time-

Seriously- they are cruzing—-
08-17-17 Big things going on in the past two days at Winnisquam Marine !!!!

This is Construx two days on the site- AMAZING !!!!
08-12-17 Heavy Duty piers to hold all those triple log pontoon boats

And there is going to be a lot of them…
Mas-Con is making GREAT progress on the foundation to building #2. AND the timing looks good !!!!

Once building #1 is up and looking good, Construx can move right onto building #2!
08-09-17 Construx arrives onsite to begin construction of building #1. YAYYYYYY !!!!

And the first building starts going up Monday 08-14-17.