11-01-17 After losing 3 work days because of the nor’easter Sunday evening- the construction crew gets one half of the roof completed in just two days!!!
And tomorrow Jim Hutchins Electric crew moves in to get the electric panel setup and our lighting system installed. Thanks Jim- you’ve come through as promised…
10-25-17 We’ve turned the corner!! 3 sides done and about half the front. BUT- The rain is killing us. Several lost days this week!
But the crew carries on as best they can in the rain. It’s not good to be up on the roof in the windy rain !!!!
10-23-17 The last panel going up on the third side. Just the front left to side. Two days and she’ll be sided.
The sides are certainly an important part of this building, But we want the roof. Let’s get the roof on…
10-21-17 More walls going up. Probably have 3 sides enclosed by this evening !!
The new Storage Building is going GREAT !!!!
10-19-17 Two wall are up, and counting. The guys are whipping that building into shape !!
Really, they’re getting it dome ASAP…
10-18-17 YAY !! Siding. The siding is going up !!
6 days and Building #2 should be sided. Bout Time !!
10-18-17 She’s a beauty. All primary and secondary steel installed. Looking good !!
All ready for siding and roofing.
And we now have boats in Building #1 !! The winter boat storage season is alive and well at the Winnisquam Marine Rt. 106 Boat Storage Facility
And all those triple logs are looking good and safe in their winter homes. They’re just waiting to be tucked in now with the winter curtain…
10-14-17 And building #2 has doors! No walls, or roof, but we do have doors. Starting Tuesday 10-17-17 we will have walls.
Some walls, not all of them at once…
10-02-17 Panoramic of the site on a nice sunny Monday !!! (Please click on me!!)
Awesome day to build a building…