07-22-17 The first concrete pier has the form peeled off and now it’s curing awaiting Construx to start the building assembly !

So far – so good…
07-22-17 Mas-Con has poured all the footings and several of the piers for building #1. This building will hold 96 boats.

96 boats, 3 high in racks. Construx should be standing this building up sometime in the next 2 weeks !!!!
Nutter Construction is manufacturing structural fill for the new building platforms !!

They sort the fill, crush some rocks and pile the fill up ready for use.
07-01-17 Hazy, Hot and Humid leads to late afternoon thunder-boomers !!!

Which makes it a great time to grill on the deck…
07-01-17 WOW !!! The Merc Verado is one beautiful engine. Twin screw supercharged, tuned exhaust.

07-01-17 It just doesn’t get any better.
07-01-17 It’s July!! Everybodies out there at the Sandbar! It’s Hazy, Hot and Humid out there !!

07-01-17 Â Yes it’s very nice to be boating…
06-16-17 Real Progress Continues at Winnisquam Marine’s new Boat Storage Facility. Room for 300+ inside, nice and cozy!!

Nutter Construction is on the job with great organization and it’s going well !!
06-16-17 After a beautiful boating week- Time out for a ducky day !!!

Look closely! But Saturday and Sunday are clearing for more good boating weather…
06-09-17 Progress on the new Winnisquam Marine Rt. 106 Boat Storage Facility continues !!!!

Nutter Construction continues to make GREAT progress right of the bat !!! They rough in the new access road so their big machines can get to the top of the site. Great job guys !!!!
06-07-17 Winnisquam Marine starts construction on our new Rt. 106 Boat Storage Facility

312 boats in inside storage buildings. State of the art racking and security features. Get on the list for a nice, dry, safe spot for your boat next winter.