08-25-17 Building #2 foundation is ready and waiting for building #2. The floor will be poured first 9/5+9/6.
Bring it on….
08-25-17 Ed’s taking good care of the 2017 Bennington QX/350hp Mercury Verado up on a pontoon boat lift for some lucky customer
Nice and dry up on the lift. Not even touching the water. Covered up every night. It doesn’t get any better…
08-25-17 The 230v and the low voltage 3 inch conduits are in the trenches !!! All set for electrical power and our 32 camera 4K resolution security cameras…
Looking good for all the powered systems…
08-25-17 Out for a late summer evening cruise on Lake Winnisquam !!!!
AND roughing it !!!!
08-25-17 Roofed!! Building #1 is roofed by Construx. Can’t wait for the side walls !!!!
Make your winter storage reservation and tell us, “you want to be in building #1”.